某承包商中标一高速公路工程项目,包括一条全长 4567m 的隧道,属特长公路隧道,根据地质详勘报告,隧址区域地下水分布广泛,地表、地下水力联系十分复杂, 岩溶、高压富水的发育受岩性与构造控制,岩溶构造及富水主要发育在观音峡背斜两翼的三叠系雷口坡组和嘉陵江组地层中,同时,本隧道所穿越的地表水库、泉眼、鱼塘密布,地下水资源丰富,岩溶分布规模不均,隧道施工遇高压涌水、突泥风险性较 高;且进、出口须家河地层地段含煤而引起的瓦斯聚集,因此,施工期间,应针对上 述重大工程地质问题在全隧道开展综合地质超前预报工作,采取双侧壁导坑法施工, 如下图所示。
项目部还实行安全目标管理,采取了一系列措施,要求进入隧道施工现场的所有人员必须经过专门的安全知识教育,接受安全技术交底,编制相应的施工组织设计,其中:
(1)当隧道遇到岩溶、高压富水危害时,可按其对隧道产生的影响情况及施工条件,采取相应施工措施。采用多打眼、打浅眼,控制爆破药量减少对围岩的扰动的光面爆破施工方法。为获得良好光面爆破效果,采取确定装药量,并通过掏槽眼和辅助眼为周边眼爆破创造临空面等措施。周边眼装药结构如下图所示。
(2)根据地勘报告揭示,本隧道地下水处理实施“排堵结合,定量堵水,限量排放,综合治理” 的治水原则。当洞内排水对地下水环境影响较大,实施以保护水环境为目的注浆堵水措施,当可能产生涌水突泥施工灾害时,实施以保证施工安全为目的注浆加固措施,衬砌背后采用压注水泥砂浆 防水,压浆顺序:应从上而下,从无水、少水的地段向有水或多水处。
(3)2010 年 4 月 3 日上午,隧道开挖时,出现溶洞涌水事故,当场导致死亡 2 人,重伤 12 人, 经补报并核实,截至 2010 年 4 月 5 日,确认累计死亡达 3 人。
【背景资料】某施工单位承担了一矿井井底车场的施工,该井底车场为常见的环形车场,排水系统由两条独立的水仓构成,施工单位所编制的工程施工网络计划如下图所示。所有的施工工序时间都已不能再缩短。
在开工前组织了图纸会审,由设计单位主持,建设单位和施工单位参加,设计单位说明拟建工程的设计意图和设计技术说明;施工单位形成正式文件的图纸会审纪要,作为与设计文件同时使用的技术文件和指导施工的依据,同时作为建设单位与施工单位进行工程结算的依据。
工程施工中发生了以下事件:
事件一:巷道交岔点D施工时,由于开挖断面大,施工单位采取了短进尺、预支护、早封闭的技术措施,确保了工程质量和安全,但施工进度慢,延误工期10d。
事件二:主井绕道工程E施工中发现围岩的稳定性很差,与地质资料提供的条件不符,施工单位采取了加强支护的措施来保证工程质量,但延误工期20d,增加施工成本20万元。
事件三:水仓入口工程G施工时,因施工单位安排失误,发生工程延误,延误工期20d,并影响了其后续工程内水仓M和外水仓N的正常施工。
Shakespeare’s lifetime was coincident with a period of extraordinary activity and achievement in the drama. (46) By the date of his birth Europe was witnessing the passing of the religious drama, and the creation of new forms under the incentive of classical tragedy and comedy. These new forms were at first mainly written by scholars and performed by amateurs, but in England, as everywhere else in western Europe, the growth of a class of professional actors was threatening to make the drama popular, whether it should be new or old, classical or medieval, literary or farcical. Court, school, organizations of amateurs, and the traveling actors were all rivals in supplying a widespread desire for dramatic entertainment; and (47) no boy who went to a grammar school could be ignorant that the drama was a form of literature which gave glory to Greece and Rome and might yet bring honor to England.
When Shakespeare was twelve years old the first public playhouse was built in London. For a time literature showed no interest in this public stage. Plays aiming at literary distinction were written for schools or court, or for the choir boys of St. Paul’s and the royal chapel, who, however, gave plays in public as well as at court. (48) But the professional companies prospered in their permanent theaters, and university men with literary ambitions were quick to turn to these theaters as offering a means of livelihood. By the time that Shakespeare was twenty-five, Lyly, Peele, and Greene had made comedies that were at once popular and literary; Kyd had written a tragedy that crowded the pit; and Marlowe had brought poetry and genius to triumph on the common stage--where they had played no part since the death of Euripides. (49) A native literary drama had been created, its alliance with the public playhouses established, and at least some of its great traditions had been begun.
The development of the Elizabethan drama for the next twenty-five years is of exceptional interest to students of literary history, for in this brief period we may trace the beginning, growth, blossoming, and decay of many kinds of plays, and of many great careers. We are amazed today at the mere number of plays produced, as well as by the number of dramatists writing at the same time for this London of two hundred thousand inhabitants. (50) To realize how great was the dramatic activity, we must remember further that hosts of plays have been lost, and that probably there is no author of note whose entire work has survived.
背景材料:
某施工单位承建城镇道路改扩建工程,全长2km,工程项目主要包括:(1)原机动车道的旧水泥混凝土路面加铺沥青混凝土面层:(2)原机动车道两侧加宽、新建非机动车道和人行道;(3)新建人行天桥一座,人行天桥桩基共设计12根,为人工挖孔灌注桩,改扩建道路平面布置如图1所示,灌注桩的桩径,桩长见表 1—1。


施工过程中发生如下事件:
事件一:项目部将原已获批的施工组织设计中的施工部署:
非机动车道(双侧)→人行道(双侧)→挖孔桩 →原机动车道加铺,改为: 挖孔桩→非机动车道(双侧)→人行道(双侧)→原机动车道加铺。
事件二: 项目部编制了人工挖孔桩专项施工方案,经施工单位总工程师审批后上报总监理工程师申请开工,被总监理工程师退回。
事件三:旧水泥混凝土路面加铺前,项目部进行了外观调查,并采用探地雷达对道板下状况进行扫描探测,将旧水泥混凝土道板的状况分为三种状况:A为基本完好;B为道板面上存在接缝和裂缝;C为局部道板底脱空、道板局部断裂或碎裂。
事件四:项目部按两个施工队同时进行人工挖孔桩施工,计划显示挖孔桩施工需57天完工,施工进度计划见表1-2。为加快工程进度,项目经理决定将⑨、⑩、⑪、⑫号桩安排第三个施工队进场施工,三队同时作业。

目前我国已有多只公募REITs产品上市,市场运行平稳,流动性和价格发现机制总体较好。当前,证监会正在会同相关部委,进一步深入推进基础设施REITs试点,完善制度机制,拓宽试点范围,更好发挥公募REITs的功能作用,进一步促进投融资良性循环,助力实体经济发展。根据以上材料,回答问题:
背景资料:
某公司承建一城市高架桥施工,该标段为5联连续梁桥,跨径组合为3×30m+(4×30m)×3+3×30m,每跨布置5片箱梁。上部结构施工采用先简支后连续施工方法,下部结构墩柱基础采用混凝土钻孔灌注桩。施工中发生如下事件:
事件一:钻孔施工及泥浆循环系统示意图如下图所示,其中D为钻头、E为钻杆、F为钻机回转装置,G为输送管,泥浆循环如图中箭头所示方向。

事件二:监理工程师巡视时发现,一钻孔的垂直度不符合要求,要求施工单位立即整改。
事件三:桩基施工过程中,施工单位采取了如下做法:
(1)桩基混凝土的坍落度为180~220mm。
(2)水下混凝土灌注前,对导管进行气压试验。
(3)灌注混凝土过程中注意测量混凝土顶面高程,灌注至桩顶设计标高时即停止施工。