【背景资料】某施工单位承包了一条21.7km的二级公路,路面面层为沥青混凝土,基层为水泥稳定碎石。其中K22+300~K22+700路段,地面横坡陡于1:5,填方平均高度为12 m左右。施工单位填筑前,对地基原状土进行了检测,土的强度符合要求,然后对地基进行了压实处理。由于前后路段开挖后,可调运利用的填料主要是石方,为节约用地,降低建设成本,在请示建设单位后。施工单位将填土路基变更为填石路基,边坡为1:1.5。为了加快施工进度,采用了倾填的方式进行施工,在路床底面下1.0 m范围内改为分层填筑并压实。在整个施工过程中,施工单位对石方路基进行了质量检验。路堤填筑完毕后不久,该路段出现了部分边坡坍塌。经处理后,该项目通过验收,评定为合格工程。
【案例三】
某高速公路N合同段路基工程施工,工期18个月,其中K23+200~K32+200路段以填方为主,合同段附近地表土主要是高液限黏土(液限值在38~49之间),在较远地带分布有腐殖土、生活垃圾土、盐渍土、淤泥、冻土、砂性土、粉土、黏性土、砾土等。出于控制造价的考虑,业主要求就地取材。为此,施工单位针对高液限土填筑路堤做了试验路段,以确定其最大干密度和松铺厚度等指标。
施工单位先对路基横断面进行测量放样,待场地清理完毕后动土触探,并绘制出横断面图,提交监理工程师复测,确认后填筑路基。
施工单位严格按照试验路段提供的数据指导施工,经过2个月的填筑,发现按试骏路段数据控制施工,每层的填筑周期超过5天,在雨期,填筑周期达到15天以上,无法满足工期要求。业主在了解了情况后,书面要求监理工程师指示施工单位在半个月后变更路堤填料。经过现场考查并征得监理工程师同意和设计单位确认后,选择了砾土与砂性土两种路堤填料,施工单位随即组织施工。另外,施工单位还制定了雨季施工的控制措施,保证质量。
由于变更后取用的路堤填料需增加较长运距,而在合同中没有该变更的价格,整个工程完工后,施工单位向业主提出了变更工程价款的报告。
【背景资料】
某施工单位承接了北方沿海地区某高速公路B合同段施工任务,该段有一座36mX40m的预应力混凝土简支箱梁桥,合同工期为15个月;采用长度为40~50m、直径为Ф1.5m的桩基础,桥位处地层土质为亚粘土;下部结构为圆柱式墩、直径为Ф1.3m,柱顶设置盖梁,墩柱高度为4~12m,桥台为重力式U型桥台。项目部为了降低成本,制订了先进的经济合理的施工方案。项目部的预制场和混凝土搅拌站布置示意图如下图所示。

桩基础采用旋挖钻机成孔;墩柱钢筋骨架现场整体制作、吊装就位;墩柱施工采用钢模板,整体拼装完成后一次吊装就位,再在顶部钢筋四周插入木楔,让钢筋骨架居中,使钢筋保护层厚度得到有效控制。项目部根据施工组织设计提出了水泥、钢材、碎石和砂等几项大宗材料的采购计划,并邀请了几家材料供应商参加竞标。项目部组织了评标小组,为节约成本,评标的唯一标准就是价格,项目部最终选择了一家报价最低的材料供应商。
问题:
【背景资料】
某热力管线暗挖隧道,长1.4km,断面有效尺寸为3.2m×2.8m,埋深3.5m。隧道穿越地层为砂土层和砂砾层,除局部有浅层滞水外,无须降水。
承包方A公司通过招标将穿越砂砾层段468m隧道开挖及初期支护分包给B专业公司。
B公司依据A公司的施工组织设计,进场后由工长向现场作业人员交代了施工做法后开始施工。
施工后,B公司在距工作竖井48m时,发现开挖面砂砾层间有渗水且土质松散,有塌方隐患。B公司立即向A公司汇报。经有关人员研究,决定采用小导管超前加固技术措施。B公司采用劈裂注浆法,根据以往经验确定注浆量和注浆压力,注浆过程中地面监测发现地表有隆起现象,随后A公司派有经验的专业技术人员协助B公司研究解决。
质量监督部门在工程竣工前例行检查时,发现A公司项目部工程资料中初期支护资料不全,部分资料保留在B公司人员手中。
【背景资料】
北方某石化公司工程项目,其一期项目工程内容包括:1套4万吨/年废硫酸综合回收装置,1套8万吨/年液化气深加工生产装置,以及与两套装置相匹配的附属设备、工艺管道安装和原料系统管道安装施工。
按设计及整体规划厂区内将建成液化气罐区、异辛烷罐区等8个相对独立的配套罐区,其中6个异辛烷储罐共计12000m³;16个液化气球罐共计36000 m³;22个卧式储罐(储存介质为丙烷、丁烷和戊烷等)共计约5400 m³;工艺管道和各系统罐体进行射线无损探伤检查;焊接检验合格后重点控制管道和罐体系统试验;待罐体和所有附件及其他与罐体焊接的构件全部完工并检验合格后,组织储罐充水试验,试验介质采用洁净水(氯离子含量小于25ppm)、水温控制在5℃以上、充水试验过程中打开透光孔,并进行基础沉降观测。
该公司项目部明确各级各类人员的安全生产责任制,以加强项目的安全管理,组织编制管道焊接施工方案。为了加强施工作业的安全,项目部组织进行了安全技术交底。施工过程中安装公司组织了与工程对应的季节性检查、专项检查,以保障施工过程安全。
施工过程中,发生了下列事件:
1.在系统管道安装施工中,由于厂外暂无电源供给。为加快施工进度,该公司自行采用自备电源组织了施工。
2.厂内工艺管道焊接后经射线探伤发现,焊接合格率偏低。项目部组织人员按质量预控的施工因素进行了分析。经查验,工艺文件已按程序审批,并进行了技术交底。但焊接记录中有部分焊材代用,部分焊机不符合要求,焊缝外观检查有漏检。根据分析结果,找出了失控原因,经整改后焊接合格率得到了提高。
How does your reading proceed? Clearly you try to comprehend, in the sense of identifying meanings for individual words and working out relationships between them, drawing on your implicit knowledge of English grammar. (41) _______ You begin to infer a context for the text, for instance, by making decisions about what kind of speech event is involved: Who is making the utterance, to whom, when and where.
The ways of reading indicated here are without doubt kinds of comprehension. But they show comprehension to consist not just of passive assimilation but of active engagement in inference and problem-solving. You infer information you feel the writer has invited you to grasp by presenting you with specific evidence and clues. (42) _______
Conceived in this way, comprehension will not follow exactly the same track for each reader. What is in question is not the retrieval of an absolute, fixed or “true” meaning that can be read off and checked for accuracy, or some timeless relation of the text to the world. (43) _______
Such background material inevitably reflects who we are. (44) _______ This doesn’t, however, make interpretation merely relative or even pointless. Precisely because readers from different historical periods, places and social experiences produce different but overlapping readings of the same words on the page--including for texts that engage with fundamental human concerns--debates about texts can play an important role in social discussion of beliefs and values.
How we read a given text also depends to some extent on our particular interest in reading it. (45) _______ Such dimensions of reading suggest--as others introduced later in the book will also do--that we bring an implicit (often unacknowledged) agenda to any act of reading. It doesn’t then necessarily follow that one kind of reading is fuller, more advanced or more worthwhile than another. Ideally, difficult kinds of reading inform each other, and act as useful reference points for and counterbalances to one another. Together, they make up the reading component of your overall literacy, or relationship to your surrounding textual environment.
[A] Are we studying that text and trying to respond in a way that fulfils the requirement of a given course? Reading it simply for pleasure? Skimming it for information? Ways of reading on a train or in bed are likely to differ considerably from reading in a seminar room.
[B] Factors such as the place and period in which we are reading, our gender, ethnicity, age and social class will encourage us towards certain interpretations but at the same time obscure or even close off others.
[C] If you are unfamiliar with words or idioms, you guess at their meaning, using clues presented in the context. On the assumption that they will become relevant later, you make a mental note of discourse entities as well as possible links between them.
[D] In effect, you try to reconstruct the likely meanings or effects that any given sentence, image or reference might have had: These might be the ones the author intended.
[E] You make further inferences, for instance, about how the text may be significant to you, or about its validity--inferences that form the basis of a personal response for which the author will inevitably be far less responsible.
[F] In plays, novels and narrative poems, characters speak as constructs created by the author, not necessarily as mouthpieces for the author’s own thoughts.
[G] Rather, we ascribe meanings to texts on the basis of interaction between what we might call textual and contextual material: between kinds of organization or patterning we perceive in a text’s formal structures (so especially its language structures) and various kinds of background, social knowledge, belief and attitude that we bring to the text.
【背景资料】某矿尾矿库属平地型,20世纪60年代末期建成并投入使用。经三次加高扩容后,尾矿库总坝高为28.0 m,总库容约1600×104m³。根据以往工程勘察资料和补充工程勘察结果,该矿编制了第四次尾矿库加高扩容方案,并于2020年5月11日开始坝体加高施工。
2020年5月25日2时许,尾矿库西北坝段发生溃坝事故,造成3人死亡,1人失联。溃坝事故发生后,该矿立即向当地政府主管部门报告事故情况,全力开展现场应急救援和事故善后工作。当日15时,事故所在地市政府组织的事故调查组赶到现场,启动事故调查工作。
经调查统计,本次事故造成尾矿输送管路损失370万元、坝体工程损失1700万元、在建工程损失130万元、丧葬及抚恤费用540万元、处理环境污染费用20万元、停产损失3200万元。
事故调查组发现,该矿尾矿车间安全培训、班前会等流于形式,隐患排查不全面、治理不到位。调查组查阅了尾矿库生产运行记录以及历次加高扩容设计施工方案,未发现有关坝基存在隐患的记录。
为进一步查明溃坝原因,事故调查组安排施工了 2个工程勘察钻孔。经与原有工程勘察资料对比分析发现,坝区原始地形以下30〜50 m存在未发现的采空区。事故调查组从尾矿车间退休人员处了解到,第三次加高后在库区听到过沉闷的放炮声,矿山曾派管理人员跟班调查但未发现问题,对此主要负责人未进一步深究。事故调查组走访得知,库区下部存在矿体,周边矿山在多年前越界进入该区域进行过采矿作业。
根据资料 (1) 至 (4),下列各项中,上述业务对甲公司 2022 年度营业利润的影响正确的是 ( )。
减少 69600 元
减少 68400 元
减少 88400 元
减少 89600 元
【案例二】
某小流域治理工程,位于长江中下游,工程包括堤防退建、河道开挖、河道裁弯取直和穿堤建筑物等工程,施工中发生如下事件:
事件1:用于部分堤防填筑的土料场共2个,料场1地势较高,料场2地势较低。施工前:对料场进行了调查取样,料场的土质、储量符合设计要求,料场1的土料含水率接近施工控制下限,料场2的土料含水率偏大。
事件2:穿堤建筑物工程,包括基坑开挖、混凝土工程、建筑物回填及同建筑物连接的堤防等工程,施工单位根据工程进度安排和各个部位的土方挖、填工程量,制订了土方调配平衡方案。
事件3:为保证工程质量,施工单位制订了质量控制方案,明确所有单元工程都应当实行“三检制”,并在自检合格的条件下,经监理单位验收合格后,方可进行下道工作。
事件4:工程施工过程中,项目法人及时组织进行了单位工程验收、阶段验收和专项验收。
案例二
【背景资料】
A公司为某水厂改扩建工程总承包单位。工程包括新建滤池、沉淀池、清水池、进水管道及相应的设备安装。其中设备安装经招标后由B公司实施。施工期间,水厂要保持正常运营。新建清水池为地下式构筑物。池体平面尺寸为128m×30m,高度为7.5m,纵向设两道变形缝,其横断面及变形缝构造如图2-1、图2-2所示。鉴于清水池为薄壁结构且有顶板,方案确定清水池高度方向上分三次浇筑混凝土,并合理划分清水池的施工段。
A公司项目部进场后将临时设施中生产设备搭设在施工的构筑物附近,其余的临时设施搭设在原厂区构筑物之间的空地上,并与水厂签订施工现场管理协议。B公司进场后,A公司项目部安排B公司临时设施搭设在厂区内的滤料堆场附近,造成部分滤料损失。水厂物资部门向B公司提出赔偿滤料损失的要求。