【不定项选择题】

案例一

【背景资料】

某小区新建热源工程,安装了3台14MW燃气热水锅炉。建设单位通过招标投标程序发包给A公司,并在工程开工前办理了建设工程质量安全监督手续、消防审批手续以及施工许可证。A公司制定了详细的施工组织设计,并履行了报批手续。施工过程中出现了如下情况:(1)A公司征得建设单位同意,将锅炉安装工程分包给了具有资质的B公司,并在建设行政主管部门办理了合同备案。(2)设备安装前。B公司与A公司在监理单位的组织下办理了交接手续。(3)在设备安装过程中,当地特种设备安全监察机构到工地检查,发现参建单位尚未到监察机构办理相关手续,违反了有关规定。燃烧器出厂资料中仅有出厂合格证。(4)B公司已委托第三方无损检测单位进行探伤检测,委托前,对其资质进行了审核,并通过了监理单位的审批。

手机使用
微信扫一扫
分享
微信内点击右上角“…”即可分享
反馈
收藏
举报
参考答案
参考解析
【不定项选择题】

【背景资料】某施工单位承建了某一级公路工程,起讫桩号K6+000~K16+000,其中K12+420~K12+540为一座钻孔灌注桩箱型梁桥。路线施工总平面布置示意图如图5-1所示,拟建公路旁边修建了生产区、承包人驻地及汽车临时便道等,K7+000~K15+000段的汽车临时便道共9.3km,K6+000~K7+000及K15+000~K16+000段的汽车临时便道紧靠拟建公路并与拟建公路平行。桥梁东西两端路基土方可调配,桩号K14+300附近有一免费弃土坑。

在K7+000~K15+000挖填土石方调配完毕后,针对K6+000~K7+000(填方路段)和K15+000~K16+000(挖方路段),有如下两种路基土方调配方案:

方案一:K15+000~K16+000挖土方作为远运利用方调配至K6+000~K7+000填筑;

方案二:K6+000~K7+000填筑土方从桩号K6+500附近新设借土场借土填筑。

针对以上两种方案,各分项综合单价见表5。


注:当汽车运输超过第1km,其运距尾数不足0.5km的半数时不计,等于或超过0.5km的半数时按增运0.5km计算。

大桥钻孔灌注桩共20根,桩长均相同,某桥墩桩基立面示意图如图5-2所示,护筒高于原地面0.3m。现场一台钻机连续24小时不间断钻孔,每根桩钻孔完成后立即清孔、安放钢筋笼并灌注混凝土,钻孔速度为2m/h,清孔、安放钢筋笼、灌注混凝土及其它辅助工作综合施工速度为3m/h。为保证灌注桩质量,每根灌注桩比设计桩长多浇筑1m,并凿除桩头。

                            图5-2  某桥墩桩基立面示意图

该工程合同总价:6.982亿元,工期:3年,施工合同中约定,人工单价100元/工日,人工窝工补偿费80元/工日,除税金外企业管理费、利润等综合费率为20%(以直接工程费为计算基数)。施工过程中发生如下事件:

事件一:施工单位根据《公路水运工程安全生产监督管理办法》进行了如下安排:

(1)第一年计划完成施工产值2.1亿元,为保证安全生产,设置了安全生产管理机构,并配备了3名专职安全生产管理人员;

(2)依据风险评估结论,对风险等级较高的分部分项工程编制专项施工方案,并附安全验算结果,经施工单位技术负责人签字后报监理工程师批准执行。

事件二:灌注桩钻孔过程中发现地质情况与设计勘察地质情况不同,停工12天,导致人工每天窝工8工日,机械窝工费1000元/天,停工期间施工单位配合设计单位进行地质勘探用工10工日;后经设计变更每根灌注桩增长15m。(原工期计划中,钻孔灌注桩施工为非关键工序,总时差8天)

事件三:施工单位加强质量管理,根据《公路工程质量检验评定标准》,对钻孔灌注桩设置质量检验的实测项目包括:桩位、孔径、孔深、混凝土强度和沉淀厚度。

事件四:钻孔灌注桩施工中,为保证隐蔽工程施工质量,各工序施工班组在上下班交接前均对当天完成的工程质量进行检查,对不符合质量要求及时纠正,每道工序完成后由监理工程师检查认可后,方能进行下道工序。钻孔灌注桩混凝土浇筑完成后用无破损法进行了检测,监理工程师对部分桩质量有怀疑,要求施工单位再采取A方法对桩进行检测。

【不定项选择题】

[A] Set a Good Example for Your Kids

[B] Build Your Kids’ Work Skills

[C] Place Time Limits on Leisure Activities

[D] Talk about the Future on a Regular Basis

[E] Help Kids Develop Coping Strategies

[F] Help Your Kids Figure Out Who They Are

[G] Build Your Kids’ Sense of Responsibility

How Can a Parent Help?

Mothers and fathers can do a lot to ensure a safe landing in early adulthood for their kids. Even if a job’s starting salary seems too small to satisfy an emerging adult’s need for rapid content, the transition from school to work can be less of a setback if the start-up adult is ready for the move. Here are a few measures, drawn from my book Ready or Not, Here Life Comes, that parents can take to prevent what call “work-life unreadiness.”

41.

You can start this process when they are 11 or Periodically review their emerging strengths and weaknesses with them and work together on any shortcomings, like difficulty in communicating well or collaborating. Also, identify the kinds of interests they keep coming back to, as these offer clues to the careers that will fit them best.

42.

Kids need a range of authentic role models – as opposed to members of their clique, pop stars and vaunted athletes. Have regular dinner-table discussions about people the family knows and how they got where they are. Discuss the joys and downsides of your own career and encourage your kids to form some ideas about their own future. When asked what they want to do, they should be discouraged from saying “I have no idea.” They can change their minds 200 times, but having only a foggy view of the future is of little good.

43.

Teachers are responsible for teaching kids how to learn; parents should be responsible for teaching them how to work. Assign responsibilities around the house and make sure homework deadlines are met. Encourage teenagers to take a part-time job. Kids need plenty of practice delaying gratification and deploying effective organizational skills, such as managing time and setting priorities.

44.

Playing video games encourages immediate content. And hours of watching TV shows with canned laughter only teaches kids to process information in a passive way. At the same time, listening through earphones to the same monotonous beats for long stretches encourages kids to stay inside their bubble instead of pursuing other endeavors. All these activities can prevent the growth of important communication and thinking skills and make it difficult for kids to develop the kind of sustained concentration they will need for most jobs.

45.

They should know how to deal with setbacks, stress and feeling of inadequacy. They should also learn how to solve problems and resolve conflicts, ways to brainstorm and think critically. Discussions at home can help kids practice doing these things and help them apply these skills to everyday life situations.

What about the son or daughter who is grown but seems to be struggling and wandering aimlessly through early adulthood? Parents still have a major role to play, but now it is more delicate. They have to be careful not to come across as disappointed in their child. They should exhibit strong interest and respect for whatever currently interests their fledging adult (as naive or ill conceived as it may seem) while becoming a partner in exploring options for the future. Most of all, these new adults must feel that they are respected and supported by a family that appreciates them.

【不定项选择题】

华北地区某省会机场进场停机坪扩建,采用水泥混凝土面层。计划工期为三月底开工,当年竣工验收。采用工程量清单的招标方式进行招投标工作。建设单位委托有资质的造价咨询机构编制了工程量招标清单。

该工程拟采用民航工程总承包管理模式,选择必须具备场道一级资质的总承包施工单位,其中扩建停机坪部位的泛光照明等目视助航设置可以选择分包企业进行施工。

施工单位在施工前明确了场道相关工作的逻辑关系,制定了施工进度计划,绘制了网络计划图。

网络图逻辑关系及施工周期如下表所示:

【不定项选择题】

认沽期权的卖方 ( )。

A.

 在期权到期时,有买入期权标的资产的权利

B.

 在期权到期时,有卖出期权标的资产的权利

C.

 在期权到期时,有买入期权标的资产的义务 (如果被行权)

D.

 在期权到期时,有卖出期权标的资产的义务 (如果被行权)

【不定项选择题】

A公司承接一项DN1000mm天燃气管线工程,管线全长4.5km,设计压力4.0MPa,材质为聚乙烯管(SDR11),除穿越一条宽度为50m的非通航河道采用泥水平衡法顶管施工外,其余均采用开槽明挖施工,B公司负责该工程的监理工作。

工程开工前,A公司踏勘了施工现场,调查了地下设施、管线和周边环境,了解水文地质情况后,建议将顶管施工改为水平定向钻施工。经建设单位同意后办理了变更手续。A公司编制了水平定向钻施工专项方案,建设单位组织了包含B公司总工程师在内的5名专家对专项方案进行了论证,项目部结合论证意见进行了修订,并办理了审批手续。

为顺利完成穿越施工,参建单位除研究设定钻进轨迹外,还采用专业浆液现场配制泥浆液。以便在定向钻穿越过程中起到如下作用:软化硬质土层、调整钻进方向、润滑钻井,为泥浆马达提供保护。

项目部按所编制的穿越施工专项方案组织施工,施工完成后在投入使用前进行了管道吹扫、强度试验、严密性试验。


【不定项选择题】

【背景资料】某安装公司承建—高层商务楼的机电工程建设项目,该高层建筑处于闹市中心,有地上30层,地下3层,工程改建的主要项目有变压器、成套配电柜的安装调试;照明配电箱及照明灯具安装;母线安装,主干电缆敷设;进口监控设备、出入口识读设备的验收安装;热水供暖管道的安装;空调机组和风管的安装、风管系统的漏风量测试;电梯安装;冷水机组、水泵、冷却塔和空调水主管的安装。
安装公司在购买监控设备、出入口识读设备时,考虑了产品的品牌和生产地,应用实践以及供货渠道和供货周期等信息。
安装公司安装配电箱和灯具及热水供暖管道的施工图如下图:


金属热水供暖管道顶点工作压力为0.1MPa,安装公司安装完成热水供暖管道后,对其进行了水压试验,水压试验压力为0.2MPa。监理工程师认为水压试验压力不符合规范要求,要求安装公司进行整改。
安装公司在进行检验批验收时,验收的项目包括:室内供暖管道水压试验、风管系统的漏风量测试、电梯试运行、灯具装饰面整平、卫生器具给水配件安装。经检验主控项目全部验收合格。

【不定项选择题】

【背景资料】

某拦湖大坝加固改造工程发包人与施工单位签订了工程施工合同,合同中估算工程量为8000m³,单价为200元/m³,合同工期为6个月,有关付款条款如下:
(1)开工前发包人应向施工单位支付合同总价20%的工程预付款;
(2)发包人自第一个月起,从施工单位的工程款中,按5%的比例扣留保留金;
(3)当累计实际完成工程量不超过估算工程量10%时,单价不调整;超过10%时,对超过部分进行调价,调价系数为0.9;
(4)工程预付款从累计工程款达到合同总价的30%以上的下一个月起,至合同工期的第五个月(包括第五个月)平均扣除。
施工单位每月实际完成并经监理单位确认的工程量见表1F420140-9。

【不定项选择题】

【背景资料】某大型矿井采用立井开拓方式,主井直径6.0m,井深890m;副井直径7.0m,井深850m;设计巷道断面较大,井底装载硐室在主井车场水平以下。
建设单位提供的地质资料中,基岩段涌水量小于10m³/h。施工单位经建设单位同意安排主井比副井提前3个月开工,装载硐室随井筒同时施工;主井进行临时改绞,用临时罐笼提升。
实际施工中,副井施工较顺利,预计可按时到底。主井地面预注浆效果较差,施工的涌水量达65m³/h。施工单位通过增加排水设备,强行通过了含水层。由于涌水影响,预计主井将比副井滞后2.5个月到底。主、副井短路贯通需2个月。经研究,决定临时改绞的方案不变。

【不定项选择题】

某城市道路改造工程,道路长1200m,路面为沥青混凝土;随路建设雨水、污水、中水和供热等管线,雨水方沟采用2.8m×3.2m钢筋混凝土结构,底板、顶板厚度均为350mm,垫层厚100mm。中水管道覆土厚度1.5m,供热管道覆土厚度2m。道路横断面布置见图3-1。道路范围内有现况D400污水管道。场地土层以填土、黏质粉土、砂卵石为主,局部存在上层滞水。

 

图3-1 道路横断面布置示意图(尺寸单位:mm)

开工前,项目部编制了施工组织设计,对各管道、机非混行道、人行道等拟定总体施工顺序为:A→雨水方沟→中水管道→B→机非混行道→C。管线沟槽施工前进行现况D400污水管道改移。雨水方沟、污水管道和中水管道合槽施工,沟槽采用土钉墙支护;供热管道单独开槽,放坡开挖。

 

沟槽开挖断面见图3-2。

施工组织设计报监理审批,监理工程师认为图3-2中缺少降雨、上层滞水处理措施,要求项目部补充。

雨污水沟槽开挖后,局部尚未支护的边坡出现渗水、开裂等失稳迹象,项目部立即采取应急措施稳定边坡,保证沟槽安全。


【不定项选择题】

【背景资料】为响应国家“节能减排、上大改小”的环保要求,某水泥厂把原有的一条日生产1000t的湿法生产线,在部分设备不变动的基础上,改成日产1000t的干法生产线(改建工程),同时将前几年因资金困难中途停建的一条日产4000t干法生产线恢复建设(复建项目);另外征用土地,再独立建设一条日产8000t干法生产线(新建项目)。建设单位实施三项工程各自独立核算,分别管理,以PC承包形式分别招标投标。最终A、B、C公司分别承担了三种不同类型的工程,C公司还同时承担了全厂110kV变电工程。工程以固定综合单价计算,工程量按实调整,并明确施工场地、施工道路、100t以上大型起重机及其操作驾驶员由建设单位提供。施工过程中发生下列事件:
事件1:A公司在设备采购时,在性价比方面对制造厂商进行了咨询,从中选择了备选厂商。进行了邀请招标。然而在制造过程中仍出现个别厂商因交通运输不便或生产任务过于饱和拖延了交货期;个别厂商因加工能力不足或管理不善满足不了质量要求。
事件2:B公司在施工过程中,因设备延期交付,延误工期5d,并发生窝工费及其他费用5万元:150t起重机在吊装过程中因驾驶员操作失误致使起重机零部件部分损坏造成停工4d,发生窝工费2万元;因大暴雨成灾停工3d;设备安装工程量经核实增加费用4万元;因材料涨价,增加费用20万元;非标准件制作安装因设计变更增加费用16万元。
事件3:C公司完成110kV变电站的施工后,编制了变压器送电试运行方案,变压器空载试运行12h,记录了变压器的空载电流和一次电压,在验收时没有通过。
事件4:在球磨机基础验收时,未能对地脚螺栓孔认真检查验收,致使球磨机的地脚螺栓无法正常安装。