【不定项选择题】

【背景资料】某10联现浇预应力混凝土连续箱梁桥地处山岭重丘区,跨越河谷,起点与另一特大桥相连,终点与一隧道相连。部分桥跨布置示意图如图4-1所示。

该项目在招投标和施工过程中发生如下事件:
事件一:招标文件中的设计文件推荐连续箱梁采用移动模架法施工,因现场场地受限,模架在该桥梁终点处的隧道内拼装,然后前移逐孔施工。但某施工单位进场后,发现隧道标未开工(另一施工单位承担该隧道施工),无法按时提供移动模架拼装场地。经桥梁施工单位提出,建设单位、设计单位和监理单位确认,暂缓第十联施工,而从第九联开始施工。因第九联桥墩墩身较高,移动模架采用桥下组拼、整体垂直提升安装方案,第十联箱梁待隧道贯通后采用桩柱梁式支架(第十联支架布置示意图见图4-2)施工,由此造成工期推迟一个月。上述方案上报相关单位并经批复后开始施工,根据相关规定,施工单位提出了以下索赔要求:
①移动模架桥下组拼场地处理费用;
②工期延长一个月按天索赔增加的现场管理费;
③移动模架垂直提升安装费用;
④第十联支架摊销费用;
⑤因第十联改为支架而损失的模架摊销费。

事件二:图4-2所示的桩柱梁式支架由桩基础、钢管柱、卸落装置、贝雷片、型钢、联接件等组成,支架按设计计算设置了施工预拱度。组拼完成后,按相关要求进行检验及加载预压试验,满足要求后投入使用。
事件三:施工单位按照《公路工程施工安全技术规范》要求,编制了支架施工专项方案,该方案经施工单位审核,由技术负责人签字后,报监理工程师审查批准后实施。

【不定项选择题】

【背景资料】
某水利枢纽由混凝土重力坝、引水隧洞和电站厂房等建筑物组成。最大坝高123m,水库总库容2×108m³,电站装机容量240MW。混凝土重力坝剖面图见下图。

本工程在施工中发生如下事件:
事件一:施工单位根据《水工建筑物水泥灌浆施工技术规范》(DL/T 5148-2014)和设计图纸编制了帷幕灌浆施工方案,计划三排帷幕孔按顺序A→B→C依次进行灌浆施工。
事件二:施工单位根据《水利水电工程施工组织设计规范》(SL 303-2017),先按高峰月浇筑强度初步确定了混凝土生产系统规模,同时又按平层浇筑法计算公式Qh ≥Kh SD/(t1-t2),复核了混凝土生产系统的小时生产能力。
事件三:施工单位根据《水工混凝土施工规范》(SL 667-2014),对大坝混凝土采取了温控措施。首先对原材料和配合比进行优化,降低混凝土水化热温升,其次在混凝土拌合、运输和浇筑等过程中采取多种措施,降低混凝土的浇筑温度。

【不定项选择题】

【背景资料】
某新建高速铁路工程,包含一座特大桥。该桥长3180m,其中有一联预应力混凝土连续箱梁,桥跨为(60+100+60)m,其余为桥跨32m预制后张箱梁;墩高为20~45m。
施工过程中,发生以下事件:
事件一:特大桥高墩采用翻模施工,翻模系统由三节模板组成,施工流程为:基础顶面清理→X→第一、二、三节钢筋绑扎→Y一→第一、二、三节混凝士浇筑及养护→第四、五节钢筋绑扎→Z→第四、五节混凝土浇筑及养护→进行下一循环施工。
事件二:连续箱梁采用挂篮法施工,挂篮现场组拼完成后,项目经理部质检人员检查了挂篮安装质量,只进行了静载试验,预压值为最大施工荷载的1.1倍,准备投入使用。
事件三:技术人员编制的连续箱梁预应力张拉技术交底资料显示:纵向预应力筋张拉应在梁段混凝土强度达到设计值的90%、弹性模量达到设计值的95%后进行,且必须保证张拉时混凝土的龄期不小于4d。
事件四:技术人员编制的运架箱梁技术交底资料显示:运梁车起步及运行时应缓慢平稳,当运梁车接近架桥机时应降速至2km/h,之后方可喂梁;梁体达到设计平面位置后,应先落在千斤顶临时支点上,调整支点高程和反力,满足要求后方可撤除千斤顶;临时支点千斤顶拆除前,遇有紧急情况时,需经项目技术负责人同意,架桥机方可过孔继续架梁。

【不定项选择题】

[A] The first and more important is the consumer’s growing preference for eating out; the consumption of food and drink in places other than homes has risen from about 32 percent of total consumption in 1995 to 35 percent in 2000 and is expected to approach 38 percent by 20This development is boosting wholesale demand from the food service segment by 4 to 5 percent a year across Europe, compared with growth in retail demand of 1 to 2 percent. Meanwhile, as the recession is looming large, people are getting anxious. They tend to keep a tighter hold on their purse and consider eating at home a realistic alternative.

[B] Retail sales of food and drink in Europe’s largest markets are at a standstill, leaving European grocery retailers hungry for opportunities to grow. Most leading retailers have already tried e-commerce, with limited success, and expansion abroad. But almost all have ignored the big, profitable opportunity in their own backyard: the wholesale food and drink trade, which appears to be just the kind of market retailers need.

[C] Will such variations bring about a change in the overall structure of the food and drink market? Definitely not. The functioning of the market is based on flexible trends dominated by potential buyers. In other words, it is up to the buyer, rather than the seller, to decide what to buy .At any rate, this change will ultimately be acclaimed by an ever-growing number of both domestic and international consumers, regardless of how long the current consumer pattern will take hold.

[D] All in all, this clearly seems to be a market in which big retailers could profitably apply their scale, existing infrastructure and proven skills in the management of product ranges, logistics, and marketing intelligence. Retailers that master the intricacies of wholesaling in Europe may well expect to rake in substantial profits thereby. At least, that is how it looks as a whole. Closer inspection reveals important differences among the biggest national markets, especially in their customer segments and wholesale structures, as well as the competitive dynamics of individual food and drink categories. Big retailers must understand these differences before they can identify the segments of European wholesaling in which their particular abilities might unseat smaller but entrenched competitors. New skills and unfamiliar business models are needed too.

[E] Despite variations in detail, wholesale markets in the countries that have been closely examined-France, Germany, Italy, and Spain-are made out of the same building blocks. Demand comes mainly from two sources: independent mom-and-pop grocery stores which, unlike large retail chains, are too small to buy straight from producers, and food service operators that cater to consumers when they don’t eat at home. Such food service operators range from snack machines to large institutional catering ventures, but most of these businesses are known in the trade as “horeca”: hotels, restaurants, and cafes. Overall, Europe’s wholesale market for food and drink is growing at the same sluggish pace as the retail market, but the figures, when added together, mask two opposing trends.

[F] For example, wholesale food and drink sales come to $268 billion in France, Germany, Italy, Spain, and the United Kingdom in 2000-more than 40 percent of retail sales. Moreover, average overall margins are higher in wholesale than in retail; wholesale demand from the food service sector is growing quickly as more Europeans eat out more often; and changes in the competitive dynamics of this fragmented industry are at last making it feasible for wholesalers to consolidate.

[G] However, none of these requirements should deter large retailers (and even some large good producers and existing wholesalers) from trying their hand, for those that master the intricacies of wholesaling in Europe stand to reap considerable gains.

41.

42.

43.

44.

[E]

45.


【不定项选择题】

某安装公司承接一项柴油加氢装置压缩单元扩建工程,工程内容包括压缩机组、桥式起重机、工艺管道、电气自动化仪表等安装。
压缩机组由机身、中体、气缸、曲轴、活塞、中间冷却器、缓冲罐、管道等组成。属于压力容器的中间冷却器、缓冲罐安装在厂房一层,压缩机本体安装在厂房二层。压缩机组散件到货,单件最大起重量为9.6t。
工程开工后,安装公司编制了压缩机组吊装运输专项施工方案,因厂房内检修用桥式起重机不能满足机组部件吊装要求,采用了在设备吊装上设置吊点,由卷扬机-滑轮组系统提升机组部件至二层平台,利用搬运小坦克配合手拉葫芦牵引设备部件至基础,再用千斤顶就位的起重运输工艺方法。
压缩机初步找正合格后,作业人员采用双表法进行联轴器对中找正。百分表安装后两轴同时转动,根据百分表读数计算轴向、径向偏差。联轴器找正示意图及轴向、
径向偏差如图3所示。联轴器找正用百分表检定合格并在有效期内。
压缩机组润滑系统油循环前,技术员在进行工艺检查时,发现系统油管路上漏装1支热电偶。在润滑系统油循环过程中,回油管视镜显示系统回油不畅,经分析处理后排除故障。

【不定项选择题】

根据资料(2),下列各项中,甲公司决定提取任意盈余公积和分派现金股利会计处理正确的是()。

A.
提取盈余公积: 借;盈余公积——任意盈余公积10 贷:利润分配一提取任意盈余公积10
B.
决定分派现金股利: 借:盈余公积 40 贷:应付股利 40
C.
提取盈余公积: 借:利润分配——提取任意盈余公积10 贷:盈余公积一—任意盈余公积10
D.
决定分派现金股利: 借:利润分配——应付现金股利或利润40 贷:应付股利 40
【不定项选择题】

案例三

【背景资料】

某城市桥梁工程,为预应力混凝土连续梁,采用挂篮悬臂浇筑法施工。挂篮质量与梁段混凝土的质量比控制在0. 3~0.5。经试验,挂篮端的允许最大变形值符合要求。悬臂浇筑段前端标高时考虑了预拱度设置。

施工过程中为了加快施工进度,项目部从其他工地借来一台千斤顶与项目部现有的油泵配套使用。

【问题】


【不定项选择题】

【背景资料】某成套配电装置安装工程项目,建设单位通过公开招标的方式选择了具有相应资质的施工单位A公司,双方签订了机电安装工程施工总承包合同,合同约定主要设备及材料由建设单位提供。A公司与一家劳务分包公司B签订劳务分包合同,将某分部工程的劳务作业分包给B公司。施工过程中,由于建设单位供应的工程材料延迟进场,使B公司停工待料,B公司直接向建设单位提出延长工期的要求。项目进行到母线施工阶段,监理工程师在检查母线连接方案时,发现有如下内容:
(1)母线加工后应保持清洗,并在接触面上涂上凡士林。
(2)当母线平置时,螺栓应由上向下穿入。
(3)用螺栓连接的母线,应在单侧加平垫圈,螺母侧应装有弹簧垫圈。
(4)母线的螺栓连接必须采用力矩扳手紧固。
(5)母线与设备连接前,应进行母线接地电阻的测试,并进行耐压试验。
该电气装置工程项目竣工验收合格后,A公司将其交付给建设单位。在保修期间,有部分设备运行不正常甚至有部件损坏,主要原因有:①设备制造质量问题,②建设单位工艺操作失误,③安装精度问题,建设单位与A 公司因质量问题的责任范围发生争执。

【不定项选择题】

某市政公司,中标某市地下隧道工程,其中竖井平面尺寸为20m×7m,深19m,竖井穿越地层为<1><2><3><4><5>,其中上部<1><2><3><4>为杂填土、饱和砂黏土、粉细砂、黄土等软弱土层,下部<5>为中风化岩石层。

为确保区间隧道施工顺利进行,先进行竖井和马头门进洞施工,竖井施工程序如下:①竖井回填;②封底;③竖井开挖;④浇筑钢筋混凝土支撑;⑤提升设备安装;⑥锁口圈梁施工;⑦井口开挖⑧挖孔桩施工;⑨测量放线。为防止马头门施工发生土体坍塌,项目部采用管棚沿轮廓线按照一定角度插入地层。管棚施工程序如下:①封口②注浆③压入钢管④水平钻孔⑤钻机就位⑥测放孔位。

由于上部地层土质软弱,竖井的围护结构设计为密排60根Ø100cm的人工挖孔桩,平均桩深为20m,超灌高度为桩长的4%。设三道钢筋混凝土支撑,上部人工开挖,下部经与勘察、设计、监理单位研究后确定了作业方式。

公司项目部编制了挖孔桩及竖井开挖专项施工方案,专家论证时认为方案中工作井的安全防护不到位,人工挖孔桩也存在下列问题:

(1)护壁搭接长度不足;(2)外加剂不合理;(3)拆模时混凝土强度未达到要求;

由于工期紧张,为了加快施工进度,在项目实施过程中还发生如下事件:

事件一:马头门采用“长进尺、快支护、紧封闭”的原则施工。

事件二:井壁底板、侧墙、拱部同时破除作业。

事件三:停止开挖时,未对掌子面进行封闭。

【问题】 

【不定项选择题】

某铁矿以16号勘探线为界划分为南北两区,井下采切工程、采矿作业由8个外委施工单位承担,施工与生产人员千余人。
北区采用斜井开拓方式,距斜井井底车场变坡点15m处设有躲避硐室,硐室东壁为砖砌墙,外抹水泥砂浆,硐室长×底宽×高为6m×3m×3m,中间为铝合金隔断,隔断靠近硐室南部有一扇铝合金推拉门,宽约600mm。硐室东侧靠近北墙东西方向摆放有由床板搭成的床、办公用桌和放电话的小桌子,南墙有一个存放靴子和工作服的铁皮箱,隔断外基本没有放置其他物品。
隔断内和隔断外拱顶部各有一盏照明灯。据详细询问,该照明灯为普通200W白炽灯,其线路由信号硐室引入,并沿硐室南墙通过拱顶连线,电压等级为220V,照明开关为拉线开关,还有一空气开关,固定在铝合金隔断内框上。
2009年7月11日9时30分,某民爆公司运送14箱炸药和600发导爆管雷管至该铁矿北区斜井井口。炸药由施工队工人用矿车运送至井底车场,一部分转运放置于躲避硐室内。
10时10分左右,施工队爆破工领取600发导爆管雷管,撕下塑料包装,用软绳捆绑在一起,徒步经斜井人行道送至井下。导爆管雷管被运送至躲避硐室内,此时多名工人在躲避硐室处等待领取炸药和导爆管雷管。10时25分,躲避硐室内发生爆炸。事故共造成16人死亡,6人受伤,直接经济损失1000余万元。
根据以上情景,回答下列问题: