某商务中心由四幢大楼(百货楼、宾馆、办公楼和综合楼)组成,A公司承包了某商务中心的机电工程,机电工程内容有建筑给水排水、建筑电气、通风空调、消防工程和电梯安装工程。商务中心还建设了一个地下变电所、水泵房和锅炉房,机电工程的冷水机组、锅炉、变配电设备和电梯等大型设备均由业主采购。合同约定百货楼、宾馆应分别提早竣工验收,A公司项目部按业主要求编制了施工总进度计划,项目部合理地选择施工方案,加快施工进度。项目部还编制了质量预控方案,在施工中设置了质量控制点,并加强进场材料的验收,使工程质量验收合格。
Write an e-mail of about 100 words to a foreign teacher in your college, inviting him/her to be a judge for the upcoming English speech contest.
You should include the details you think necessary.
You should write neatly on the ANSWER SHEET.
Do not sign your own name at the end of the E-mail. Use “Li Ming” instead.
Do not write the address. (10 points)
某商务中心由四幢大楼(百货楼、宾馆、办公楼和综合楼)组成,A公司承包了某商务中心的机电工程,机电工程内容有建筑给水排水、建筑电气、通风空调、消防工程和电梯安装工程。商务中心还建设了一个地下变电所、水泵房和锅炉房,机电工程的冷水机组、锅炉、变配电设备和电梯等大型设备均由业主采购。合同约定百货楼、宾馆应分别提早竣工验收,A公司项目部按业主要求编制了施工总进度计划,项目部合理地选择施工方案,加快施工进度。项目部还编制了质量预控方案,在施工中设置了质量控制点,并加强进场材料的验收,使工程质量验收合格。
【背景资料】
某水利水电枢纽由拦河坝、溢洪道、发电引水系统、电站厂房等组成。水库库容为 12×108m3。拦河坝为混凝土重力坝,最大坝高 152m,坝顶全长 905m。 重力坝抗滑稳定计算受力简图如图 3 所示
图 3 重力坝抗滑稳定计算受力简图
事件一: 混凝土重力坝以横缝分隔为若干坝段。根据本工程规模和现场施工条件,施工单位将每个坝段以纵缝分为若干浇筑块进行混凝土浇筑。每个坝段采用竖缝分块形式浇筑混凝土。
事件二:混凝土重力坝基础面为岩基,开挖至设计高程后, 施工单位对基础面表面松软岩石、棱角和反坡进行清除,随即开仓浇筑。
事件三: 混凝土重力坝施工中, 早期施工时坝体出现少量裂缝,经分析裂缝系温度应力所致。施工单位编制了温度控制技术方案,提出了相关温度控制措施,并提出出机口温度、表面保护等主要温度控制指标。
事件四: 本工程混凝土重力坝为主要单位工程,分为 18 个分部工程,其中主要分部工程 12 个。单位工程施工质量评定时,分部工程全部合格,优良等级 15 个,其中主要分部工程优良等级 11 个。施工中无质量事故。外观质量得分率 91%。
背景资料
某建设单位投资兴建一办公楼,建筑面积21000㎡;钢筋混凝土框架—剪力墙结构,地上18层,层高3.6m。招标文件约定招标文件规定安全文明施工费可采取有竞争性报价。
施工单位对中标的工程造价进行了分析,费用构成情况是:人工费1500万元,材料费7000万元,机械费1200万元,管理费890万元,措施项目费809万元,利润700万元,规费600万元,税金300万元,预付款按价款15%进行计算。
施工过程中,发出设计变更指令,在变更指令下发后第15天,施工单位向监理工程师提出该项变更的估价申请。设计变更附加工程费用为3000万元,工程原工期为12个月。监理工程师收到变更估价申请,经审核无误后提交建设单位。次月底,施工单位在上报已完工程进度款支付申请时,建设单位提出变更设计增加款项只能在竣工结算前最后一期的进度款中支付。施工单位对此提出异议。
Within the span of a hundred years, in the seventeenth and early eighteenth centuries, a tide of emigration—one of the great folk wanderings of history—swept from Europe to America. (46) This movement, driven by powerful and diverse motivations, built a nation out of a wilderness and, by its nature, shaped the character and destiny of an uncharted continent.
(47) The United States is the product of two principal forces—the immigration of European peoples with their varied ideas, customs, and national characteristics and the impact of a new country which modified these traits. Of necessity, colonial America was a projection of Europe. Across the Atlantic came successive groups of Englishmen, Frenchmen, Germans, Scots, Irishmen,
Dutchmen, Swedes, and many others who attempted to transplant their habits and traditions to the new world. (48) But the force of geographic conditions peculiar to America, the interplay of the varied national groups upon one another, and the sheer difficult of maintaining old-world ways in a raw, new continent caused significant changes. These changes were gradual and at first scarcely visible. But the result was a new social pattern which, although it resembled European society in many ways, had a character that was distinctly American.
(49) The first shiploads of immigrants bound for the territory which is now the United States crossed the Atlantic more than a hundred years after the 15th-and-16th-century explorations of North America. In the meantime, thriving Spanish colonies had been established in Mexico, the West Indies, and South America. These travelers to North America came in small, unmercifully overcrowded craft. During their six- to twelve-week voyage, they survived on barely enough food allotted to them. Many of the ships were lost in storms, many passengers died of disease, and infants rarely survived the journey. Sometimes storms blew the vessels far off their course, and often calm brought unbearably long delay.
To the anxious travelers the sight of the American shore brought almost inexpressible relief. Said one recorder of events, “The air at twelve leagues’ distance smelt as sweet as a new-blown garden.” The colonists’ first glimpse of the new land was a sight of dense woods. (50) The virgin forest with its richness and variety of trees was a real treasure-house which extended from Maine all the way down to Georgia. Here was abundant fuel and lumber. Here was the raw material of houses and furniture, ships and potash, dyes and naval stores.
某新建电气化铁路,主跨为(56+100+56)m连续梁,主跨采用三跨预应力连续箱梁,两端边跨为后张法预应力T梁,主跨穿越既有线营运铁路,既有铁路营运养护、运营归某铁路局管理,铁路局下设专业站段,包括机务段、房建段、车务段、给水段、电务段、供电段、工务段等。两端的车站归车务段管辖。
在铁路边进行桥梁基础施工前,项目经理部分别制定了桥梁基础和跨线铁路挂篮施工方案和安全措施,方案与措施中包含了对铁路设备设施的保护措施。
新建电气化铁路牵引变电所位于山区小镇山腰上。所内设两组V/X接线,40MVA 牵引变电器,每组V/X接线牵引变压器由2台单相变压器组成。主变运输所使用车辆是重型牵引车辆,轴数6轴,轮数22条,车辆长度18m,宽度3m,装车后高度4.6m,车货重量75t,转弯半径7m,车辆每轴最大承重14t。为满足车辆最小转弯半径,需在高速公路上设置临时出口,然后修建运输便道,途经小镇居民区和民用便桥、涵洞等建筑设施。
【背景资料】
某招标人就一河道疏浚工程进行公开招标,招标公告分别在“中国招标投标公共服务平台”和该省水行政主管部门指定的某网站刊登。在某网站刊登的招标公告要求投标人购买招标文件时须提交信用等级材料,而在“中国招标投标服务平台”的招标公告无此条要求。
招标文件的合同条款按照《水利水电工程标准施工招标文件》(2009年版)和《堤防和疏浚工程施工合同范本》编制,并约定如下内容:
(1)本工程保修期为1年,自工程通过合同完工验收之日起计算;
(2)疏浚土方的工程量增加超过15%视为变更,超出部分相应结算单价减少10%。
共有A、B、C、D、E五家投标人参加开标会议。
投标人A投标人投标文件的投标涵盖有企业及企业法定代表人的印章,但没有加盖项目负责人的印章。某位评标人以此为理由判定投标人A的投标文件无效。
投标人B在评标过程中,针对标底价格的合理性提出异议。
投标人C的投标报价最高,故在开标后第二天撤销了其投标文件。
最终,评标委员会推荐投标人E为第一中标候选人。招标人确定投标人E为中标人,并与之签署施工承包合同。
施工过程中,投标人E首先进行充填区围堰清基。清基完成后,投标人E未通知监理人到场验收即进行后续施工。监理人在其施工几日后,要求投标人E进行局部开挖,以检查清基工作质量。经检查,监理人确认投标人E的清基质量合格。该月投标人提出结算单,见表,并要求工期顺延1天。

【背景资料】
某公路工程采用工程量清单方式招标,甲公司中标并与发包人签订了施工承包合同,甲公司项目部编制了工程施工进度双代号网络计划图(如图1所示),监理工程师批准了该计划。(时间单位:天)
合同约定当工程量增加超出清单工程量10%时,双方可以协商调整超出10%部分的单价,甲公司部分工程量清单报价见表1。
施工中发生如下事件:
事件1:由于设计变更,路基挖土方实际完成工程量为90000m3,双方协商调整单价为14元/m3。边沟人工清淤挖运20m实际完成工程量82m3。
事件2:工作D施工过程中,罕见特大暴雨天气使一台施工机械受损,机械维修费花费2万元,同时导致工作D实际时间比计划时间拖延8d。
事件3:施工单位租赁的施工机械未及时进场,使工作F实际时间比计划时间拖延8天,造成施工单位经济损失2000元/d
事件4:业主变更设计,未及时向施工单位提供图纸,使工作E实际时间比计划拖延20d,造成施工单位经济损失1500元/d。
事件5:D工作完成后,业主委托第三方检验,检验结果质量为不合格。承包商返工修复完工后,业主重新委托第三方检验。由于D工作返工,影响了F工作的开始时间,业主要求承包商赶工,监理工程师也需要一起加班。
【案例三】
某工程公司中标承包一城市主干道项目,该道路一半为新铺设路面,另一半为利用再生剂重新翻新路面。在旧沥青中加入低黏度的胶结料——再生剂,能够调节过高的黏度并使脆硬的旧沥青混合料软化,便于充分分散,和新料均匀混合,从而达到翻新路面的目的。
部分非主体结构施工根据相关规定分包给具有资质的某单位。该主干道为沥青混合料面层,新铺设路面施工作业时正值冬季。
在施工现场进口处,项目经理部设置了五牌一图。
在整个项目竣工验收前,总包单位在没有收集分包单位施工资料的情况下,直接递交了整个项目的施工资料。