案例(三)
背景资料:
某公司承建一埋地燃气管道工程,采用开槽埋管施工。该工程网络计划工作的逻辑关系见表2 -1;
表2-1网络计划工作逻辑关系

项目部按表2-1绘制网络计划图如图2-1所示:

图2-1网络计划图(缺项)
网络计划图中的El、E2工作为土方回填和敷设警示带,管道沟槽回填土的部位划分为Ⅰ、Ⅱ、Ⅲ区,如图2-2所示:

回填土中有粗砂、砂土、碎砖土可供选择。
【背景资料】某大型海上工程孤立墩混凝土承台施工,其混凝土的配合比(胶凝材料∶砂∶碎石)为1∶1.50∶2.50,水胶比为0.40,胶凝材料总用量为444kg/m3。混凝土的初凝时间为1.5h,终凝时间为5.0h,承台的平面尺寸为10m×10m,承台底标高为+1.0m(理论深度基准面,下同),顶标高为+5.0m。9根直径1.2m的大管桩伸入承台混凝土中2m。
承台施工时桩芯混凝土已提前灌注完成。
施工水域潮汐为规则半日潮,施工日的潮汐表见表2。因承台尺寸较大,施工用非水密模板。采用有效生产能力为50m3/h的混凝土拌合船,承台混凝土分两次浇筑。第一次浇筑厚度为1.0m,分四层浇筑,自下而上分别为300mm、300mm、200mm、200mm。海上浇筑混凝土要在水位以上进行振捣,在初凝前底层混凝土不宜被水淹没。

案例(三)
背景资料:
某公司承建一埋地燃气管道工程,采用开槽埋管施工。该工程网络计划工作的逻辑关系见表2 -1;
表2-1网络计划工作逻辑关系

项目部按表2-1绘制网络计划图如图2-1所示:

图2-1网络计划图(缺项)
网络计划图中的El、E2工作为土方回填和敷设警示带,管道沟槽回填土的部位划分为Ⅰ、Ⅱ、Ⅲ区,如图2-2所示:

回填土中有粗砂、砂土、碎砖土可供选择。
(41) Teri Byrd
I was a zoo and wildlife park employee for years. Both the wildlife park and zoo claimed to be operating for the benefit of the animals and for conservation purposes. This claim was false. Neither one of them actually participated in any contributions whose bottom line is much more important than the condition of the animals.
Animals despise being captives in zoos. No matter how you “enhance” enclosures, they do not allow for freedom, a natural diet or adequate time for transparency with these institutions, and it's past time to eliminate zoos from our culture.
(42) Karen R. Sime
As a zoology professor, I agree with Emma Marris that zoo displays can be sad and cruel. But she underestimates the educational value of zoos.
The zoology program at my university attracts students for whom zoo visits were the crucial formative experience that led them to major in biological sciences. These are mostly students who had no opportunity as children to travel to wilderness areas, wildlife refuges or national parks. Although good TV shows can help stir children's interest in conservation, they cannot replace the excitement of a zoo visit as an intense, immersive and interactive experience.Surely there must be some middle ground that balances zoos' treatment of animals with their educational potential.
(43) Greg Newberry
Emma Marris's article is an insult and a disservice to the thousands of passionate who work tirelessly to improve the lives of animals and protect our planet. She uses outdated research and decades-old examples to undermine the noble mission of organization committed to connecting children to a world beyond their own.
Zoos are at the forefront of conservation and constantly evolving to improve how they care for animals and protect each species in its natural habitat. Are there tragedies? Of course. But they are the exception not the norm that Ms. Marris implies. A distressed animal in a zoo will get as good or better treatment than most of us at our local hospital.
(44) Dean Gallea
As a fellow environmentalist animal-protection advocate and longtime vegetarian. I could properly be in the same camp as Emma Marris on the issue of zoos. But I believe that well-run zoos and the heroic animals that suffer their captivity so serve a higher purpose. Were it not for opportunities to observe these beautiful wild creatures close to home many more people would be driven by their fascination to travel to wild areas to seek out disturb and even hunt them down.
Zoos are in that sense similar to natural history and archeology museums serving to satisfy our need for contact with these living creatures while leaving the vast majority undisturbed in their natural environments.
(45) John Fraser
Emma Marris selectively describes and misrepresents the findings of our research. Our studies focused on the impact of zoo experiences on how people think about themselves and nature and the data points extracted from our studies.
Zoos are tools for thinking. Our research provides strong support for the value of zoos in connecting people with animals and with nature. Zoos provide a critical voice for conservation and environmental protection. They afford an opportunity for people from all backgrounds to encounter a range of animals from drone bees to springbok or salmon to better understand the natural world we live in.
2.根据资料(2),下列各项中,甲公司吸收新投资人投资的会计处理正确的是( )。
某施工单位承担了一矿井井底车场的施工,该井底车场为常见的环形车场,排水系统由两条独立的水仓构成,施工单位所编制的工程施工网络计划如下图所示。所有的施工工序时间都已不能再缩短。
在开工前组织了图纸会审,由设计单位主持,建设单位和施工单位参加,设计单位说明拟建工程的设计意图和设计技术说明;施工单位形成正式文件的图纸会审纪要,作为与设计文件同时使用的技术文件和指导施工的依据,同时作为建设单位与施工单位进行工程结算的依据。
工程施工中发生了以下事件:
事件一:巷道交岔点D施工时,由于开挖断面大,施工单位采取了短进尺、预支护、早封闭的技术措施,确保了工程质量和安全,但施工进度慢,延误工期10d。
事件二:主井绕道工程E施工中发现围岩的稳定性很差,与地质资料提供的条件不符,施工单位采取了加强支护的措施来保证工程质量,但延误工期20d,增加施工成本 20万元。
事件三:水仓入口工程G施工时,因施工单位安排失误,发生工程延误,延误工期20d,并影响了其后续工程内水仓M和外水仓N的正常施工。
【背景材料】
某桥梁桥台采用扩大基础,桥墩采用钻孔灌注桩基础。扩大基础的主要控制点如下:①基底地基承载力的确认,满足设计要求;②基底表面松散层的清理;③及时浇筑垫层混凝土,减少基底暴露时间;④基底平面位置、尺寸大小和基底标高的确认。钻孔灌注桩的主要质量控制点有:①垂直度的控制;②孔径的控制,防止缩径;③清孔质量(嵌岩桩与摩擦桩要求不同);④水下混凝土的灌注质量。
【背景资料】某公司中标高新产业园职工宿舍楼项目,建筑面积2万平方米,地上5层,由4个结构形式和建设规模相同的单体建筑组成,合同施工工期240天。
中标后,该公司根据施工项目的规模和复杂程度设置矩阵式项目管理组织结构。项目安全管理部门负责人具有注册安全工程师资格证、中级工程师证。
项目经理部根据工序合理、工艺先进的原则确定了施工顺序。本项目各单体建筑共由4个施工过程组成,分别为:地基基础工程、主体工程、装饰装修工程、安装工程。每个施工过程组建1个专业工作队,各施工过程的流水节拍见表1。
为创建绿色施工示范工程,项目部编制了《施工现场建筑垃圾减量化专项方案》,采取了施工过程管控措施,从源头减少建筑垃圾的产生。
五、【背景资料】某施工单位通过招投标以定额价格3.2折的费用承揽到通信综合楼电源设备安装工程,合同中规定“施工单位应按照设计施工。除经甲方同意,工程中发生设计以外的工作量,合同价款不予调整”。施工过程中,施工单位发现部分电源线的线径较小,因此提出改变电源线规格程式的变更申请。建设单位认为工程为包工包料的承包方式,不予追加费用,施工单位因此仍按照设计要求敷设各种电源线。由于投标报价较低,施工单位为了节约费用,将机架的保护接地端子连接到了工作接地线上。 在施工过程中,现场监理人员一直在陪同施工单位施工,观察施工单位的工作过程,并在需要签字的技术文件上都作了签字确认。 工程验收时,建设单位发现部分走线架上的缆线有交叉现象、个别机架垂直度不符合要求、电源线端头漏铜较多等问题。建设单位因此决定另选一家施工单位处理工程中的遗留问题。 在工程试运行阶段,维护人员发现接地汇集线上的部分电源线温度过高,建设单位因此请现场的其他施工单位及时更换,事故的处理结果也未上报。
某建筑工程,占地面积8000㎡,地下三层,地上三十层,框筒结构。结构钢筋采用HRB400等级,底板混凝土强度等级C35,地上三层及以下核心筒和桩混凝土强度等级为C60。局部区域为两层通报报告厅,其主梁配置了无粘结预应力筋。某施工企业中标后进场组织施工,施工现场场地狭小,项目部将所有材料加工全部委托给指定加工厂进行场外加工。
在施工过程中,发生了下列事件:
事件二:施工现场总平面布置设计中包含如下主要内容:①材料加工场地布置在场外;②现场设置一个出入口,出入口处设置办公用房;③场地周边设置3.8m宽环形载重单车道主干道(兼消防车道),并进行硬化,转弯半径10m;④在干道一侧开挖400×600mm管沟,将临时供电线缆,临时用水管线埋置于管沟内。监理工程师认为总平面布置设计存在多处不妥,责令整改后再验收,并要求补充主干道具体硬化方式和裸露场地文明施工防护措施。
张某是红叶有限公司的小股东,持股 5%; 同时,张某还在枫林有限公司任董事,而红叶有限公司与枫林有限公司均从事保险经纪业务。红叶有限公司多年没有给张某分红,张某一直对其会计账簿存有疑惑。关于本案,下列哪一选项是正确的?( )
张某可以用口头或书面形式提出查账请求
张某可以提议召开临时股东会表决查账事宜
红叶有限公司有权要求张某先向监事会提出查账请求
红叶有限公司有权以张某的查账目的不具正当性为由拒绝其查账请求
背景资料
某施工单位承建一大型厂房,施工进度双代号网络图如下所示,经过总监理工程师和建设单位确认后实施。

在进行主体结构施工时遇上了雨季,导致主体结构工程延后15天完工;在进行到屋面与室外装修施工时遇到了罕见低温天气,导致其工期延后10天;主体结构完成后,受到罕见的暴雨影响,导致其后续工作开工时间均推迟了5天。
二次结构施工开始时,为了能按原计划工期完工,项目部决定进行工期优化,本工程原计划各工作相关参数见下表: