【不定项选择题】

背景资料:

某分洪闸位于河道堤防上,河道堤防级别为5级。该闸在施工过程中发生如下事件:

事件1:闸室底板及墩墙设计采用C25W4F100混凝土。施工单位在混凝土拌合过程中掺入高效减水剂,并按照混凝土试验有关标准制作了混凝土试块,对混凝土各项指标进行试验。

事件2:为有效控制风险,依据《大中型水电工程建设风险管理规范》(GB/T50927-2013),施工单范围对施工过程中可能存在的主要风险进行了分析,把风险分为四大类:第一类为损失大、概率大的风险,第二类为损失小、概率大的风险,第三类为损失大、概率小的风险,第四类为损失小、概率小的风险,针对各类风险提出了风险规避等处置方法。

事件3:为加强工程施工安全生产管理,工程开工前,项目法人组织制定了本工程安全事故应急预案,包含了预警管理,制定了应急响应流程,包含①跟踪事态进展;②成立应急指挥部;③启动响应;④会商研究部署;⑤派遣现场工作组等。现场施工时2名施工人员不慎从作业高度为12.0m的高空坠落。

手机使用
微信扫一扫
分享
微信内点击右上角“…”即可分享
反馈
收藏
举报
参考答案
参考解析
【不定项选择题】

某市政公司中标一市郊护城河跨线桥工程,该桥结构为13m+16m+13m简支梁桥,桥台为桩柱式桥台,桥梁宽度方向为15片预制板梁,幅宽16米。因中、边梁跨度不同,边跨梁高62cm,中跨梁高82cm。桥梁纵截面如图5-1所示。(注:尺寸单位为cm,标高单位为:m)

桥梁支座系统采用矩形板式橡胶支座,其布置如图5-2所示。

由于施工期正值河流枯水期,河底平坦无水。表层淤泥平均厚度约35cm。根据地质条件,施工单位对河底部位进行处理,开辟出一片预制梁场进行预制板梁的施工。

桥梁桩基直径1.2米,采用正循环回转钻孔法施工灌注桩,施工方案中对正循环回转钻孔施工方法描述如下:利用钻具旋转切削土体钻进,泥浆输入钻孔内,从钻头的钻杆下口吸进,泥浆携带钻渣通过钻杆中心上升,从钻杆顶部连接管道排出至沉淀池内,钻渣在此沉淀而泥浆回流入泥浆池不再使用。

施工过程中发生了如下事件:

事件一:②号墩台中墩桩基混凝土浇筑中途发生了堵管,因浇筑量不大,施工单位采取提管不拔出混凝土液面,并敲击导管的方式帮助疏导管内堵塞,经疏通后继续施工完成了该中墩桩的浇筑。

事件二:为加快施工进度项目部购买了三套同型号预应力张拉设备,为使用方便,千斤顶、油泵随机组合起来张拉预应力钢绞线。由于工期紧,新设备购买后立即投入使用。

事件三:为确保张拉质量,板梁预应力施工采取“双控”控制。


【不定项选择题】
关于业务(2),下列分录表述正确的有(  )。
A.
借:固定资产30700 <br />      应交税费一应交增值税(进项税额)5100 <br />      贷:银行存款35800
B.
借:固定资产30000 <br />      应交税费一应交增值税(进项税额)5100 <br />      贷:银行存款35100
C.
2012年计提折旧分录为: <br /> 借:制造费用1750 <br />     贷:累计折旧1750
D.
2012年计提折旧分录为: 借:管理费用1750     贷:累计折旧1750
【不定项选择题】

某施工单位承担一高瓦斯矿井的运输大巷和回风大巷的施工任务。其中,B队施工回风巷,该巷断面20㎡,穿过一层厚0.5m的煤层;巷道采用锚、网、喷和U形钢支架,然后复喷混凝土的联合支护形式。在巷道即将穿过煤层前,B队队长认为煤层很薄,没有采取专门的措施,结果在穿煤层时,发生了煤与瓦斯突出,造成尚未进行复喷混凝土的10余棚支架崩倒,顶板冒落,引起3人死亡。发生事故后项目经理立即组织事故调查工作,汇报施工单位领导,同时迅速作出了恢复施工的决定。
经历此事故后,施工单位加强了安全技术管理工作,在后续施工中,遇到软岩巷道,采取了适当的支护措施,顺利通过软岩巷道区。

【不定项选择题】

【背景资料】

某公司承建一座城郊跨线桥工程,双向四车道,桥面宽度 30m,横断面路幅划分为 2m(人行道)+5m(非机动车道)+16m(车行道)+5m(非机动车道)+2m(人行道)。

上部结构为 5×20m预制预应力混凝土简支空心板梁;下部结构为构造A及φ130cm圆柱式墩,基础采用φ150cm钢筋混凝土钻孔灌注桩;重力式U型桥台;桥面铺装结构层包括厚10cm 沥青混凝土、构造B、防水层。桥梁立面如图1所示。

 

项目部编制的施工组织设计明确如下事项:

(1)桥梁的主要施工工序编号为:

①桩基、②支座垫石、③墩台、④安装空心板梁、⑤构造 A、⑥防水层、⑦现浇构造 B、⑧安装支座、⑨现浇湿接缝、⑩摊铺沥青混凝土及其他;施工工艺流程为:①桩基→③墩台→⑤构造 A→②支座垫石→⑧安装支座→④安装空心板梁→C→D→E→⑩摊铺沥青混凝土及其他。

(2)公司具备梁板施工安装的技术且拥有汽车起重机、门式吊梁车、跨墩龙门吊、穿巷式架桥机、浮吊、梁体顶推等设备。经方案比选,确定采用汽车起重机安装空心板梁。

(3)空心板梁安装前,对支座垫石进行检查验收。


【不定项选择题】

(二)丙公司为增值税一般纳税人,2019年度至2021年度发生的与无形资产有关业务如下:
(1)2019年1月10日 ,丙公司开始自行研发一项行政管理用非专利技术,截至2019年 5月31日 ,用银行存款支付外单位协作费148万元,领用本单位原材料成本52万 元(不考虑增值税因素),经测试,该项研发活动已完成研究阶段。
(2)2019年6月1日研发活动进入开发阶段。该阶段发生研究开发人员的薪酬支出70 万元,领用材料成本170万元(不考虑增值税因素),全部符合资本化条件。2019 年12月1日,该项研发活动结束,最终开发形成一项非专利技术并投入使用。该 非专利技术预计可使用年限为5年,预计残值为零,釆用直线法摊销。
(3)2020年1月1日,丙公司将该非专利技术出租给乙企业,双方约定租赁期限为2 年,每月末以银行转账结算方式收取租金5万元(不考虑增值税因素)。
(4)2021年12月31日,租赁期限届满。经减值测试,该非专利技术的可收回金额为 104万元。
要求:
根据上述资料,不考虑其他因素,分析回答下列小题。(答案中的金额单位用万元表示)
4. 根据资料(1)至(3),下列各项中,关于该非专利技术摊销的会计处理表述正确的是(  )。

A.
应当自可供使用的下月起开始摊销
B.
应当自可供使用的当月起开始摊销
C.
该非专利技术出租前的摊销额应计入管理费用
D.
摊销方法应当反映与该非专利技术有关的经济利益的预期实现方式
【不定项选择题】

 根据资料 (1) 至 (3), 使该企业本月利润表 “营业利润” 项目减少的金额是 (    ) 万元。

A.

23.1

B.

22.5

C.

23.5

D.

24.1

【不定项选择题】

【背景资料】

某大型水电站工地,施工单位在重力坝浇筑过程中,管理人员只在作业现场的危险区悬挂了警示牌,夜间施工时,不幸发生了高空坠落导致死亡3人的事故。当工程某隐蔽部位的一道工序施工结束,在未通知监理人员到场检验的情况下,为赶施工进度,项目经理就紧接着指挥完成下道工序的浇筑。工程建设期间,还时常发生当地群众到建设管理单位及施工工地聚集阻挠施工事件。

【不定项选择题】

In his autobiography, Darwin himself speaks of his intellectual powers with extraordinary modesty. He points out that he always experienced much difficulty in expressing himself clearly and concisely, but (46)he believes that this very difficulty may have had the compensating advantage of forcing him to think long and intently about every sentence, and thus enabling him to detect errors in reasoning and in his own observations. He disclaimed the possession of any great quickness of apprehension or wit, such as distinguished Huxley. (47)He asserted, also, that his power to follow a long and purely abstract train of thought was very limited, for which reason he felt certain that he never could have succeeded with mathematics. His memory, too, he described as extensive, but hazy. So poor in one sense was it that he never could remember for more than a few days a single date or a line of poetry. (48)On the other hand, he did not accept as well founded the charge made by some of his critics that, while he was a good observer, he had no power of reasoning. This, he thought, could not be true, because the “Origin of Species” is one long argument from the beginning to the end, and has convinced many able men. No one, he submits, could have written it without possessing some power of reasoning. He was willing to assert that “I have a fair share of invention, and of common sense or judgment, such as every fairly successful lawyer or doctor must have, but not, I believe, in any higher degree.” (49)He adds humbly that perhaps he was “superior to the common run of men in noticing things which easily escape attention, and in observing them carefully.”

Writing in the last year of his life, he expressed the opinion that in two or three respects his mind had changed during the preceding twenty or thirty years. Up to the age of thirty or beyond it poetry of many kinds gave him great pleasure. Formerly, too, pictures had given him considerable, and music very great, delight. In 1881, however, he said: “Now for many years I cannot endure to read a line of poetry. I have also almost lost my taste for pictures or music.” (50)Darwin was convinced that the loss of these tastes was not only a loss of happiness, but might possibly be injurious to the intellect, and more probably to the moral character.

【不定项选择题】

【背景资料】

某段铁路路基工程,主要施工内容有路堑土石方开挖、路堤填筑及附属工程。其中,路堑段长度140m,地面最大横向坡度1: 10,路堑开挖最大深度20m;路堤地基处理设计采用铺设一层土工合成材料加筋垫层;路堤邻近营业线一侧支挡设计采用扶壁式挡土墙,挡土墙结构如图3所示;部分路基边坡设计采用浆砌片石“人”字形骨架进行防护。新建路堤坡脚距离营业线坡脚最小距离为5m,施工期间营业线正常运营。

施工过程中发生以下事件:
事件1:在开挖路堑土石方时,采用横向台阶法开挖,为加快施工进度,在同一开挖地段,施工队同时进行上部台阶土石方开挖和下部台阶土石方装运。在邻近营业线路堤填筑施工时,施工队现场负责人要求把确保施工设备安全放在首位。
事件2:在土工合成材料加筋垫层施工前,项目经理部给施工队进行了技术交底,明确要求土工织物各幅之间应搭接,搭接宽度35cm,土工格栅各幅之间不需搭接,但要密排放置,连接牢固;在加筋垫层上填第一层土时,应先填中间,后填两边;压实时先用轻型压路机碾压1遍,再用重型压路机碾压至符合规范规定和设计要求。
事件3:施工队进行“人”字形骨架浆砌片石施工时,对边坡局部超挖部分采用干砌片 石砌补;浆砌片石材料选用质地坚硬、不易风化,且母岩强度等级不小于MU30,最小块径大于lOcm的片石;浆砌片石采用灌浆法砌筑。

【不定项选择题】

【背景资料】某双车道公路隧道。全长620m,地层岩性为石灰岩,地下水较丰富。有一条F断层破裂带,隧道最大埋深490m,纵坡为-3%.其围岩级别及长度见隧道纵断面示意图。


合同总工期20个月为保证施工安全,施工单位结合项目地质和设备条件,拟在全断面、台阶法、单侧壁导坑法、CD法、CRD法5种工法中选择组织施工。根据以往施工经验及该项目实际情况,施工前,相关人员经讨论分析确定隧道主要施工内容的进度计划指标为:III级围岩70-90m/月,IV级围岩50-70m/月,V级围岩30-50m/月,施工准备3个月,隧道内沟槽、路面及附属设施施工3个月。