【不定项选择题】

A公司发行一种开放式基金,该基金的认购费率为1.20%,基金的认购费用将统一按净认购金额为基础收取。

手机使用
微信扫一扫
分享
微信内点击右上角“…”即可分享
反馈
收藏
举报
参考答案
参考解析
【不定项选择题】

【背景资料】

某体能训练场馆工程,建筑面积 3300m²,律箱物长 72m,宽 45m,地上一层,钢筋混凝土框架结构,屋面采用球形网架结构。框架柱,梁均沿建筑物四周设置,框架柱轴线间距 9000mm, 框架梁截面尺寸 450mm × 900mm,梁底标高 9.6m。现场配置一部塔吊和一台汽车吊进行材料的水平与垂直运输。

本工程框架梁模板支撑体系高度 9.6m,属于超过一定规模危险性较大的分部分项工程。施工单位编制了超过一定规模危险性较大的模板工程专项施工方案。

建设单位组织召开了超过一定规模危险性较大的模板工程专项施工方案专家论证会,设计单位项目技术负责人以专家身份参会。

施工方案中,采用扣件式钢管支撑体系,框架梁模板支撑架立杆下垫设页岩砖;扫地杆距地面 250mm;架体顶层步距 1500mm;梁底支撑架立杆均采用下部一根 6m 定尺钢管与上部一根定尺短钢管搭接连接。

项目部针对工程特点,进行了重大危险源的辨识,编制了专项应急救援预案。项目部编制了绿色施工方案,确定了“四节一环保”的目标和措施。

【不定项选择题】
对驱动气瓶、驱动管路和灭火剂储瓶进行检测,下列检测结果符合要求的有( )。
A.
1"驱动气瓶驱动一区选择阀,同时驱动6"至17"CO₂储瓶
B.
2"驱动气瓶驱动二区选择阀,同时驱动1"至17"CO₂储瓶
C.
3"驱动气瓶驱动三区选择阀,同时驱动1"至17"CO₂储瓶
D.
CO₂储瓶通过称重装置吊装在储瓶框架上
E.
系统存储CO₂灭火剂的总净重714kg
【不定项选择题】

【背景资料】某公司承建一沉箱重力式码头,沉箱由公司预制场预制,每个沉箱的混凝土方量为480m3,设计沉箱混凝土抗压强度等级为C30。该预制场实际统计的混凝土立方体抗压强度标准差为3.0MPa.经计算和试配确定混凝土的施工配合比为1: 2.50: 3.50.用有效搅拌量为2.0m2的搅拌机搅拌混凝土,正常施工情况下(使用干砂、干碎石)每罐混凝土用砂1700kg,拌合水306kg.施工中遇大雨,雨后测得砂的含水率达3%(碎石雨后很快干了)。沉箱下水后浮运通过港池,该港理论深度基准面与平均海平面的高差为1.29m,港池底泥面距平均海平面6m,从当地潮汐表查得该时刻潮高2.12m,沉箱的最小稳定吃水6.5m,拖运时的富余水深取0.5m.

【不定项选择题】

【背景资料】
东北某民航机场跑道水泥混凝土道面由于常年冻融出现了大面积破损,机场拟对该跑道行旧道面加铺沥青混凝土。机场管理当局完成了相关准备工作,主要有:向民航地区管理局申请不停航施工,并按要求提交了相关材料,通过招标选定了施工单位,成立了工程指挥部等。整个工不涉及飞行程序和起飞着陆最低标准的修改。2018年6月3日空管部门发布了航行通告。
月9日,施工单位开始进场施工。
施工前,施工单位针对不停航施工组织的特点,制定了详细的施工方案,并按以下施工工序进行施工作业。施工过程中发生以下几项工作:
事件一:施工采用SMA沥青混合料,正式施工前,施工单位重点检测了沥青的主要技
术指标,并通过集料级配设计及马歇尔试验确定了沥青用量。
事件二:监理单位对施工拌合站检查时发现,材料堆放处有积水,不同材料混合堆放。
事件三:沥青混合料运至现场时,测得温度为110℃。施工单位为保证施工进度,将摊铺速度控制在5m/min,并采用双钢轮压路机和轮胎压路机组合碾压作业。

【不定项选择题】

(三)甲公司成立于2021年10月20日,法定代表人为李某。10月25日,甲公司财务人员赵某持有关资料到A银行开立基本存款账户。11月1日,甲公司从乙公司购进一批价值 30万元的货物,采用支票方式付款。12月5日,甲公司向B银行申请贷款,B银行审查符合贷款条件后向其发放贷款200万元。
要求:
根据上述资料,不考虑其他因素,分析回答下列小题。
4.甲公司从B银行贷款时开立的银行结算账户属于( )。

A.
基本存款账户
B.
一般存款账户
C.
专用存款账户
D.
临时存款账户
【不定项选择题】

【背景资料】
牛江闸为14孔开敞式水闸,设计流量为2400m³/s。每个闸墩划分为一个单元工程,其中第6号闸墩高10.5m,厚1.5m,顺水流方向长24.0m,其混凝土量为365.8m³,模板面积为509.6㎡,钢筋为30.5t。
闸墩混凝土采用钢模施工。承包人进行闸墩模板及支架设计时,考虑的基本荷载有:模板及支架自重、新浇混凝土重量、钢筋重量以及振捣混凝土时产生的荷载。监理单位发现承包人考虑的基本荷载有漏项并及时进行了纠正。
施工过程中,承包人和监理单位对第6号闸墩的混凝士模板进行了检查验收,填写的《混凝土模板工序质量评定表》如下表所示。
水利水电工程混凝土模板工序质量评定表

【不定项选择题】

【资料背景】

某酒店工程,建筑面积2.5万㎡,地下1层,地上12层。其中标准层10层,每层标准客房18间。35㎡/间;裙房设宴会厅1200 ㎡气层高9m。施工单位中标后开始组织施工施工单位企业安全管理部门对项目贯彻企业安全生产管理制度情况进行检查,检查内容有安全生产教育培训、安全生产技术管理、分包(供)方安全生产管理、安全生产检查和改进等

宴会厅施工“满堂脚手架"搭设完成自检后,监理工程师按照《建筑施工安全检查标准》

JGJ59要求的保证项目和一般项目对其进行了检查,检查结果如表5-1

表5-1 满堂脚手架检查结果(部分)

宴会厅顶板混凝土浇筑前,施工技术人员向作业班组进行了安全专项方案交底,针对混疑土浇筑过程中,可能出现的包括浇筑方案不当使支架受力不均衡,产生集中荷载、偏心荷载等多种安全隐患形式,提出了预防措施标准客房样板间装修完成后,施工总承包单位和专业分包单位进行初验,其装饰材料的燃烧性能检查结果如表5-2。

表5-2 样板间装饰材料燃烧性能检查表(部分)

注:A+B1指A级和B1级材料均有。

竣工交付前,项目部按照每层抽一间,每间取一点,共抽取10个点,占总数5.6%的抽样方案,对标准客房室内环境污染物浓度进行了检测。检测部分结果如表5-3。

表5-3标准客房室内环境污染物浓度检测表(部分)

【不定项选择题】

In his autobiography, Darwin himself speaks of his intellectual powers with extraordinary modesty. He points out that he always experienced much difficulty in expressing himself clearly and concisely, but (46)he believes that this very difficulty may have had the compensating advantage of forcing him to think long and intently about every sentence, and thus enabling him to detect errors in reasoning and in his own observations. He disclaimed the possession of any great quickness of apprehension or wit, such as distinguished Huxley. (47)He asserted, also, that his power to follow a long and purely abstract train of thought was very limited, for which reason he felt certain that he never could have succeeded with mathematics. His memory, too, he described as extensive, but hazy. So poor in one sense was it that he never could remember for more than a few days a single date or a line of poetry. (48)On the other hand, he did not accept as well founded the charge made by some of his critics that, while he was a good observer, he had no power of reasoning. This, he thought, could not be true, because the “Origin of Species” is one long argument from the beginning to the end, and has convinced many able men. No one, he submits, could have written it without possessing some power of reasoning. He was willing to assert that “I have a fair share of invention, and of common sense or judgment, such as every fairly successful lawyer or doctor must have, but not, I believe, in any higher degree.” (49)He adds humbly that perhaps he was “superior to the common run of men in noticing things which easily escape attention, and in observing them carefully.”

Writing in the last year of his life, he expressed the opinion that in two or three respects his mind had changed during the preceding twenty or thirty years. Up to the age of thirty or beyond it poetry of many kinds gave him great pleasure. Formerly, too, pictures had given him considerable, and music very great, delight. In 1881, however, he said: “Now for many years I cannot endure to read a line of poetry. I have also almost lost my taste for pictures or music.” (50)Darwin was convinced that the loss of these tastes was not only a loss of happiness, but might possibly be injurious to the intellect, and more probably to the moral character.

【不定项选择题】

【背景资料】

甲公司投资建造一座太阳能电池厂,工程包括: 1 个厂房及附属设施、1 栋办公楼、2 栋宿舍楼。甲公司按工程量清单计价规范进行了公开招标,乙公司中标,合同价 2800 万元。

双方合同约定,甲公司合同价的 10%向乙公司支付工程预付款,乙公司向甲公司提供预付款保函。签订合同后,乙公司向甲公司提交了预付款支付申请,甲公司核实后于 2020年3月1日向乙公司发出工程程预付款支付证书,并于 2020 年 3 月 21 日向乙公司支付了预付款。乙公司以合同价为基数,以 2%目标利润率预测目标成本,并按工程直按成本和间接成本进行成本分解。

乙公司在施工过程中由于资金困难,自行决定将 2 栋宿舍楼全部交给具有相应施工资质的丙公司施工,仅收取 10%的管理费。

甲公司与乙公司合同约定竣工时间为 2021 年 5 月 20 日,每延期竣工 1 天,乙公司向甲公司支付 2 万元的工期违约金。2021 年 5 月 20 日工程竣工验收时,发现宿舍楼存在质量问题,需要修复后才能使用,因工程修复于 2021 年 6 月 20 日通过了甲公司组织的竣工验收。

【不定项选择题】

案例(四):某地级市中心机房电源设备安装工程,工期5周(每周工作时间按7天计),项目部制订的进度计划见图4。

本项目实际发生的材料费与表中所列材料费一致,由施工单位采购,并按照工作量平均分摊:施工单位人工成本为500元1天/人。工程实施过程中,项目部每周实际参加人数及周末统计的已完成工作量比例见表4。

完工后,施工单位提交了竣工资料,内容包括:变更单、隐蔽工程、随工验收签证、停(复)工报告、开工报告、建筑安装工程量总表、设计变更、交(完)工报告、交接书、洽商记录、竣工图、测试记录。
施工合同未约定保修期,工程终验后第10个月,个别电池极柱发生严重腐蚀现象,经分析认定为由电池生产缺陷问题造成的。