某建设单位开发一小区高层民用住房建筑,工程内容有室内供配电、灯具安装、建筑防雷、建筑管道、消防、电梯、建筑智能化等。A 公司为机电安装项目施工总承包单位,经建设单位同意,A 公司将室内供配电、灯具安装、建筑防雷分包给了有相应资质的 B 公司。
地下一层桥架施工时,A 公司发现 B 公司安装的槽盒、导管均不符合规范要求,如下图:

B 公司进行灯具安装前,按设计图纸进行了灯具的采购,如下图所示:
B 公司在施工中,严格进行质量“三检制”最终顺利完成工程,所干工程全部验收合格。
某建设单位开发一小区高层民用住房建筑,工程内容有室内供配电、灯具安装、建筑防雷、建筑管道、消防、电梯、建筑智能化等。A 公司为机电安装项目施工总承包单位,经建设单位同意,A 公司将室内供配电、灯具安装、建筑防雷分包给了有相应资质的 B 公司。
地下一层桥架施工时,A 公司发现 B 公司安装的槽盒、导管均不符合规范要求,如下图:

B 公司进行灯具安装前,按设计图纸进行了灯具的采购,如下图所示:
B 公司在施工中,严格进行质量“三检制”最终顺利完成工程,所干工程全部验收合格。
In the movies and on television, artificial intelligence is typically depicted as something sinister that will upend our way of life. When it comes to AI in business, we often hear about it in relation to automation and the impending loss of jobs, but in what ways is AI changing companies and the larger economy that don’t involve doom-and-gloom mass unemployment predictions?
A recent survey of manufacturing and service industries from Tata Consultancy Services found that companies currently use AI more often in computer-to-computer activities than in automating human activities. Here are a few ways AI is aiding companies without replacing employees:
Companies are using artificial intelligence to remove some of the unconscious bias from hiring decisions. “There are experiments that show that, naturally, the results of interviews are
much more biased than what AI does,” says Pedro Domingos, author of The Master Algorithm: How the Quest for the Ultimate Learning Machine Will Remake Our World and a computer science professor at the University of Washington."(41)__________________________________________
"One company that's doing this is called Blendoor. It uses analytics to help identify where there may be bias in the hiring process.
Some AI software can analyze and optimize marketing email subject lines to increase open rates. One company in the UK, Phrasee, claims their software can outperform humans by up to 10 percent when it comes to email open rates. This can mean millions more in revenue. (42)______
These are “tools that help people use data, not a replacement for people,” says Patrick H.Winston, a professor of artificial intelligence and computer science at MIT.
Energy companies can use AI to help customers reduce their electricity bills, saving them money while helping the environment. Companies can also optimize their own energy use and cut down on the cost of electricity. Insurance companies, meanwhile, can base their premiums on AI models that more accurately access risk. Domingos says,“ (43) ________________________.”
“Machine learning often provides a more reliable form of statistics which makes data more valuable,” says Winston. It “helps people make smarter decisions.” (44) .
A number of companies, particularly in energy and transportation, use AI image processing technology to inspect infrastructure and prevent equipment failure or leaks before they happen. “If they fail first and then you fix them, it’s very expensive,” says Domingos. “ (45)______________________________.”
【背景资料】
某水利枢纽工程由混凝土重力坝、溢洪道和坝后式厂房等组成。发包人与承包人签订了混凝土重力坝施工合同。合同约定的节点工期要求:
(1)2005年12月1日进场准备(指“四通一平”);
(2)围堰填筑及基坑排水在2006年11月1日开始;
(3)围堰拆除及蓄水在2009年6月1日前结束。
施工项目部技术人员根据资源配置的基本条件编制了重力坝网络进度计划,其工作逻辑关系及持续时间见表1。
注:①重力坝混凝土总工程量为430万立方米;
②每月按30天计。施工过程中发生如下事件:
事件1:技术人员根据表1绘制的初始网络进度计划如图1(单位:月)。
项目部技术负责人审核时发现,表1中的工作逻辑关系及持续时间正确合理,初始网络进度计划(图1)中部分逻辑关系有错,且不能满足节点工期要求。技术人员根据审核意见重新编制了符合要求的进度计划,并上报得到批准。
事件2:由于未能及时提供场地,C1工作于2006年7月11日开始,承包人按监理人的要求采取了赶工措施,经170天完成任务,赶工费用2万元,承包人据此提出了赶工费和工期的索赔要求。
事件3:坝体混凝土浇筑初期,因对已完成混凝土质量有疑问,监理人要求承包人对已完成混凝土进行钻孔重新检验,由此增加费用4万元,承包人提出了索赔要求
事件4:重力坝混凝土浇筑,至2008年6月30日累计完成工程量为300万立方米。现场混凝土制备、运输、浇筑能力为22万立方米/月。
背景材料
某工程公司接到一个接入网新装工程,共要安装开通调测16台MDU,还要负责局端和光分侧跳纤。在安装设备时发现有1台设备的业务板灯亮的不正。跳纤时发现有2台设备的路由端口被占用。在现场拨测是发现大量端口有杂音。
背景资料
某高瓦斯矿井井下轨道大巷,围岩普氏系数(f)6,采用直墙半圆拱形断面,断面净宽3800mm,净高3400mm。永久支护为锚喷支护,金属锚杆规格22x2200mm。采用树脂药卷锚固,锚杆间排距700mmx700mm;喷射混凝土厚度100mm。强度等级C20。
该轨道大巷采用钻爆法施工、工作面爆破采用垂直楔形掏槽。掏槽眼在拱基线以下沿巷道中心线两侧对称布置,中间两个为深2000mm的空眼,周边眼、辅助眼与掏槽眼深度相同,均为2200mm,周边眼间距800mm。爆破使用三级煤矿许用炸药和总延期时间不超过130ms的煤矿许用毫秒延期电雷管,采用反向装药结构,一次装药。分次起爆,爆破后发现断面欠挖严重。
该巷道施工喷射混凝土支护的主要工序有:(1)拱部喷射;(2)冲洗岩帮并设置喷厚标志;(3)养护;(4)墙部喷射;(5)清理基础等。施工单位进行了合理安排,确保了支护工作的正常进行。
该轨道大巷当月施工90m,由专业监理工程师组织进行了验收。